Building a pool requires working to a number of factors including weather, material curing times and site conditions and of course general layout.
With over 325 pools now installed by Ultimate Pools, we have the expertise to install pools to the highest standard with efficiency.
One of the key things people ask us when they’re looking to build a pool is, “How long will it take?” There are a few factors to consider that will influence how long it will take to construct your pool. These include (but are not limited to):
- Planning your pool
- What type of pool you choose (e.g. concrete or fibreglass)
- The time of the year you build
- Approval from local authorities
- Any other contractors required
Building a pool requires working to several factors including weather, material curing times and site conditions and of course general layout.


While sites differ, the general installation process will look similar between pools.
Day 0: Prior works completed and signed off (site specific i.e retaining)
Day 1: Site Clearing and Access
Day 1: Excavations & groundworks
Day 1-2: Pool Placement (Crane in / Hi-Ab / Digger lift) prep ground and base (a few hours to 1 day) We allow a certain fee in the pool price some additional charges may apply to your site
Day 3-4: Plumbing from pool to pump shed + back-filling (in-ground pools) (1 – 3 days depending on distance to equipment shed and access).
Day 4: Pool room plumbing (if concrete slab has been laid).
Day 5: Pool wiring (1-2 days), you may wish to have arranged your electrician to meet us at the beginning of install week.We are often able to assist with trenching for cables at stage 2 with excavation.
Following week: Coping Stone Fitting (1-3 days)